APPENDIX T. ESTIMATES OF COST OF LOCK CANAL. [Supplemental to the minority report.] Breakwaters in Limon Bay (length 41 miles), from mile 0 to mile 3.30, using the estimate adopted by the Board-------.-.--------------------------------------------------------$5, 000, 000 Extension of breakwater, 11 miles in length, from mile 3.30 to head of Limon Bay (mile 4.55), 400,000 cubic yards, at 75 cents-------------------------------------------------------300, 000 Excavation of channel in Limon Bay, 40 feet in depth below low water and 500 feet wide, from mile 0 to mile 4.55: Earth (dredging), 8,300,000 cubic yards, at 15 cents....------------------------------------------1, 245, 000 Excavation 40 feet in depth below low water and 500 feet wide from head of Limon Bay (mile 4.55) to northerly end of Gatun locks (mile 7.15): Earth (dredging), 10,000,000 cubic yards, at 25 cents------------------------------... $2, 500, 000 Indurated clay (dredging), 2,030,000 cubic yards, at 70 cents------------------------... 1, 421, 000 3, 921, 000 Excavation for Gatun locks, mile 7.15 to mile 7.74: Earth, 920,000 cubic yards, at 40 cents...---------------------------------------------368, 000 Indurated clay, 2,740,000 cubic yards, at 70 cents. ..----------------------------------1, 918, 000 2,286,000 Gatun locks exclusive of excavation and approach walls------------------------------ . .----... 13, 075, 000 Approach walls of Gatun locks ------------------------------------------------------------------ 500,1000 Backfilling and embankment, Gatun locks, 660,000 cubic yards of borrowed earth, at 50 cents-----------. .330, 000 Gatun dam: Earth embankmentBelow elevation 50, 12,170,000 cubic yards of dredged material pumped into dam, at 20 cents. . . ..------------------------------------------------------------$2, 434, 000 Between elevation 50 and elevation 80, 5,770,000 cubic yards of dredged material pumped into dam, at 30 cents..-------------------------------------------1, 731, 000 Above elevation 80, 3,260,000 cubic yards of material from excavations placed in dam, at 25 cents. ....-------------------------------------------------------815, 000 Excavation for diversion channel and regulating worksEarth, 1,100,000 cubic yards, at 40 cents..---------------------------------------440, 000 Indurated clay, 480,000 cubic yards, at 70 cents.---------------------------------336, 000 Concrete in regulating works and for protection of diversion channel, 189,000 cubic yards, at $8. .. ..-------------------------------------------------------------1, 512, 000 Regulating gates and machinery (complete).----------------------------------------320, 000 Allowance for preparatory work at site of Gatun dam and miscellaneous expenses ...... 200, 000 Total for Gatun dam.....---------------------------------------------------------------7, 788, 000 Excavation from Gatun locks (mile 7.74) to Obispo (mile 31.25), making channel 45 feet deep and not less than 500 feet wide for 23.51 miles, of which 15.92 miles is not less than 1,000 feet wide: Earth excavation in the dry, 600,000 cubic yards, at 40 cents-------------------------$240, 000 Indurated clay excavation at Gatun, 130,000 cubic yards, at 70 cents------------------91, 000 Earth excavation (dredging), 12,960,000 cubic yards, at 25 cents.---------------------3, 240, 000 Rock excavation in the dry, 1,160,000 cubic yards, at $1.15-------------------------.. 1, 334, 000 4,905,000 Cutting trees in Gatun Lake.....-------------------------------------------------------------------100, 000 Excavation from mile 31.25 to mile 32.80, channel 45 feet deep and 300 feet wide, with slopes of 10 vertical to 1 horizontal: 7,280,000 cubic yards, at 80 cents. ...----------------------------------------------$5, 824, 000 4619i-5 A-06 -38 425