18 . PANAMA RAIL ROAD COMPANY. \ Extension of the Cristobal Mole. The preliminary borings for the extension of the Cristobal mole, which were commenced on February 9, 1916, were finally completed in Septem- ber, 1916. On June 10, 1916, work was started on a trestle to be used for dumping soft rock for an extension to the Cristobal mole; this work was completed March 17, 1917. Approach Fill for Pier 6 and Fill for Track Yard. The construction of the approach fill and fill for track yard for Pier 6 was started on June 12, 1916, and by December 31 of the fiscal year 1916- 1917 the work was completed with a total quantity of 129,448 cubic yards in place at a total cost of $45,327.42, or $0.35 per yard. Boat Landing and Launch House Between Piers 7 and &. Work on this boat landing and launch house was commenced on Sep- tember 15, 1916. All work on the substructure was completed with the completion of the concreting of the cylinders on May 27, 1917. It has not been possible to do any further construction work on the boat landing due to the fact that no floor steel has yet been received. Improvements 7n Roadways. In February, 1917, a new 30-foot road for an entrance to the docks was commenced and completed in April. The surface in front of Piers 8 and 9, which was formerly grass plot, was also concreted over, increasing to a great degree traffic facilities of the docks. The area in front of the new local freight warehouse was also concreted. Pier 6. Construction of Pier 6 was commenced July 21, 1916. Congress has appropriated for this the sum of $1,500,000.00. It is expected to com- plete all work on the cylinders not later than November, 1917, and to complete the work on the concrete floor by May, 1918, at which date the paving of the floor may be started provided no delay may be encountered in securing the shed steel. It is believed this pier will be completed on or before December 31, 1918, when same will be turned over to the Panama Rail Road Company for operation. Serer OF HXPENDITURES UnpER AppRovep A. F. Es. For AMOUNT. A. F. BE. No. 580: Construction Terminal Docks, Cristobal..... ES CaS cS ogi suae area ancl oe $867 83 6502 Construction Vilasonic hemplens..0 a i oe ee 536 78 (49> ~ Construction Lerminal Dock No. 7, Cristobal. s...6 «05. k en et 106,843 09 742 Repairing Track and Installation 60 Switches, Cristobal Yard...... 2,469 71 753 Construction Concrete Freight House, Panama................... 7,001 02 779 Driving Dolphins for Tying up Colliers, Cristobal................. 40 95 (35: .. Extension of Mole at Bier No. 7 Cristobal... 2:53... 53.64..0.5:.. 4,450 87 802 Construction of Refrigeration and Ice Manufacturing Plant, Balboa. 8,019 72 805 Repairs to Erect De Mayo Coal Conveyors on Barges 18 and 20, TISBO Wales cee ee essl oa Geode SNS ee 87 50 807 Construction and erecting 12 Booms for De Mayo. Conveyors on Piste Srang: 9. Cristobal: oe ee 171 60 808 Electrical installation of De Mayo Conveyors on. Docks 8 and 9, Cristobal ee apes i er ne ee Heater aiase 159 15 310 Repairs to Barges 13 and 19 for De Mayo @onvevorse 2. she ce. 24 05 $13 Manufacturing one coal screen for screening lump coal............ 31 19 828 Construction ice cream and milk bottling plant, Cristobal......... 19,804 61