° REPORT OF THE PANAMA RAILROAD COMPANY. dk MAINTENANCE OF WAY AND STRUCTURES. The total expenses have increased $138,143.89 over 1907, or 31. 33 per cent, due principally to large forces necessary to keep up new tracks on fills and to heavy rail, tie and switch renewals. The coming year will show a decrease in maintenance expense because physical conditions are excellent and the second main track embankment has had most of its settlement. Track department.—The second main line has been completed and is now in use between milepost 74 and milepost 364, milepost 404, and milepost 464, and 1 mile of the La Boca branch, a total of 352 miles of double main track. During the year 45,000 ties, 52,000 cubic yards of gravel, and 25,000 cubic yards of crushed rock have been used. New side, house, and commissary tracks laid with 70-pound steel have been constructed as follows: Sidetracks. | House tracks. | - Commissary Total. : | acks Location. Jv aa ae eas Bl a Se i eC a Le Sree 7G | No. | Length. No. | ee No. a Length, No. | Length. as | ae a SBS Ve Dee | | ! | Feet | Feet. | Feet | Feet. MUOTCA NECLO One es eee [eioe Sapna ee ates ela OTT es ee coe aa gene les 911 ETO LOS soe eee EN ee as | 12] PASO aie tees ee coe iio ata ieee te 23 PSam Pablo 6 oe 1, 202 | fete is ese oe ee Laie e208 GOES ORE ae ee ee Sen oe se ae | 1 | EADO ee [Nearer cree le enos cpio bee 1} 1, 450 Tas: Cascadas: sis oes ae es [Soe e [Sees ee (eee eee 1 | 1,100 1 1, 100 CUS eye es at oe Re eras Mier Pes ee pee ea ' ra [255] 1 590 | 2 1,315 PedrogMigiieloe ei ss ei ae ee [apes eeereani eee Rea he eau ee ihe Od | 1 515 Mina Oreste Sls Sues, SRE ae sea He Sea ee ee jester is Oe ote Negue on ee 1 | 1, 120 ovale chen. seins: Stee pe ae se oa ea 4008 2 86 3 a 2,265) ~ 91 47,909 a Pincade: 1,500 feet puilt dunine | 1907 at ie San Pablo, and Goreeun At Mount Hope a material yard containing 12,210 feet of track was laid for facilitating the handling of material at the Isthmian Canal Commission material and store yard. The cost of this work oe borne by the Isthmian Canal Commission, for whose use it was Ut. At Colon a temporary coach yard was taken up and a permanent one containing 1,725 feet of track built. The old terminal has also been removed and the eround filled in for quarters. This provides fifty of the choicest building lots in Colon, lying along the beach between the church and the hospital. The old Panama yard has been entirely remodeled in order to accommodate increased passenger business and facilitate the handling of freight. As now being built, the yard consists of an 8-track diamond 1,300 feet long, a terminal yard consisting of new turntable, engine house, water station, cinder pit, and machine shop on one side of the diamond, and 4 industry tracks on the other side, a 4-track passenger yard and 3 pairs of team and freight-house tr: acks 700 feet long. The team tracks and freight house are located alongside a new street that has been opened from the end of Balboa avenue at Sixteenth street to the passenger depot. The work necessitated laying the following amount of track: | Feet. New 70 pound sted 2 7, 740 S: El 70-poumd steel. 11, 510 SoG SOpound steel SS ee ee 3, 450